Sample Implementation Timeline

Koddi Ads is designed to be implemented in approximately 45 days (but we have seen partners do it in as little as 30 days). Below is a typical implementation plan.

Task Task Owner Start End
KODDI ADS CONFIGURATION
Quick Start Questionnaire Media Network Publisher Day 1 Day 7
Set Up Inventory (Entity) Feed
Note: We need a one time feed by at least day 10 to keep on track with feed configuration. A fully automated feed does not need to be in place until launch (or shortly thereafter).
Media Network Publisher Day 3 Day 10
Koddi Ads Configuration
  • Entity Feed Ingestion
  • Auction Type
  • Attribution Rules
  • Targeting
  • Branding
  • SSO
  • Initial Users
  • Global Ad Delivery
  • Koddi Day 8 Day 14
    Enable partner access Koddi Day 14 Day 14
    KODDI API INTEGRATION
    Design Ad Units All Day 8 Day 14
    Integration with Koddi APIs
    • Ad Unit Design
    • Ad Unit Build
    • Winning Ads
    • Impressions
    • Clicks
    • Conversions
    Media Network Publisher (normally 1-2 sprints of 2 weeks for a couple of developers) Day 15 (this can start earlier if your time is ready) Day 30
    TESTING & DEPLOYMENT
    End to End Testing in UAT All Day 31 Day 40
    Deployment Prep All Day 41 Day 44
    Deployment All Day 45 Day 45