Sample Implementation Timeline
Koddi Ads is designed to be implemented in approximately 45 days (but we have seen partners do it in as little as 30 days). Below is a typical implementation plan.
Task | Task Owner | Start | End |
---|---|---|---|
Quick Start Questionnaire | Media Network Publisher | Day 1 | Day 7 |
Set Up Inventory (Entity) Feed
Note: We need a one time feed by at least day 10 to keep on track with feed configuration. A fully automated feed does not need to be in place until launch (or shortly thereafter). |
Media Network Publisher | Day 3 | Day 10 |
Koddi Ads Configuration | Koddi | Day 8 | Day 14 |
Enable partner access | Koddi | Day 14 | Day 14 |
Design Ad Units | All | Day 8 | Day 14 |
Integration with Koddi APIs
Media Network Publisher (normally 1-2 sprints of 2 weeks for a couple of developers) |
Day 15 (this can start earlier if your time is ready) |
Day 30 |
|
End to End Testing in UAT | All | Day 31 | Day 40 |
Deployment Prep | All | Day 41 | Day 44 |
Deployment | All | Day 45 | Day 45 |